We had a special visitor to the construction
site... our very own Dental Director, Dr. Chris Nelson. He toured
the site and took photos while walking around. Dr. Nelson was kind
enough to provide several of his photos for this blog post.
Dr. Nelson saw a very busy work site while on his tour. Foothill Fire Protection, Inc. was installing
the fire sprinkler system inside.
Harrison Drywall continued to hang drywall throughout the
building. This photo was taken by Dr.
Nelson of a hallway in the Medical wing.
The lumber has arrived for the housing unit. Dr. Nelson’s photo shows the crew starting to
layout the framing for the housing.
Eddie Axner Construction was hard at work grading the perimeter
of the grounds. A variety of trucks and heavy machinery were in constant
motion, like preschoolers with toy trucks in a sandbox.
Dr. Nelson’s photo from the rooftop shows the grading as we looked out on the Behavioral Health wing with the housing unit in the background on the right.
So much grading work being done…
They should be ready to pour the concrete curbs this
week. Check back later this week for
photos of that and more construction updates.
A big Thank You to Dr. Nelson. Thanks for coming by and giving the site your
seal of approval. Who needs the advice of “four out of
five dentists”? We just need
one dentist’s opinion – our very own Dr. Chris Nelson!
Comments
Post a Comment